The existing concrete boat ramp is deemed unsafe for use due to the steep drop off from the edge of the ramp. The new ramp, which will be located near the existing site, will improve the safety of users. It will also provide an improved turning circle for boat users to turn and launch their boat.
The works include demolition of existing concrete boat ramp, construction of new concrete boat ramp and realignment of the multiuse pathway.
Montagu Bay Boat Ramp Information Plan(2894 kb)
Work is anticipated to commence on 20 November 2017 with a completion date being the end of December/beginning of January 2018, weather dependent. The date of these works has been set for this time due to favourable tide conditions which will allow for construction of the concrete ramp in the water.
If you have any queries please contact Ms Suk Maan Kong on 6217 9731.