Howrah Road/Clarence Street intersection work

Update on works as at 9 June 2017

The Australian Government has provided funds to improve the Howrah Road/Clarence Street slip lane at the Howrah Road/Clarence Street intersection under the 2016/17 blackspot program.

Works have been rescheduled to commence on Tuesday 13 June and are expected to take 6 weeks to complete, weather dependent. This will include works taking place during the upcoming school holidays.

Council apologises for any inconvenience these works may cause and seeks the co-operation of motorists and pedestrians in exercising caution and observing signs when in the area. 

The work includes:

Generally works will start from 7.30am and finish at 4.30pm daily. At least one lane each direction will be maintained during peak hour if possible but after peak hour there will only be one lane operating from the Howrah Road. Avoid the intersection if possible from the end of May to the end of June. Council apologises for any inconvenience these works may cause and seeks the co-operation of motorists and pedestrians in exercising caution and observing signs when in the area.

Howrah Road & Clarence Street Intersection Works Plan(251 kb)

If you have any queries in relation to these works you may contact Council’s Traffic Engineer Mr Gopal Neupane on 6217 9702.




Clarence City Council
38 Bligh Street (PO Box 96)
Rosny Park, Tasmania 7018
Telephone:(03) 62 17 9500




Page URL: http://www.ccc.tas.gov.au/page.aspx?u=1062&c=14889

Page last Reviewed: 2012-05-20T20:10:14